Hi All,
I have made setting in OPL8 (Order type dependent parameters) that Reservation will be created once the production order is Released (Reservation/Purch.Req. = 2). This setting is working fine if I am creating a production order manually via CO01. Which means upon saving of manually created order, system is not creating Reservation unless the same is Released - perfect.
However, when I am converting a Planned order into production order via CO40, the reservation is getting created right during saving, though it has not been released.
Could you please explain helping me why it is happening like this?
Thanks & regards,
PP_HKV...