Reservation created for Project Stock (Q) should check Unrestricted stock

Former Member
0 Kudos

Dear All,

In std SAP we have to transfer goods from Unrestricted to Project stock and then we can issue it to the Project.

My client requirement is that while creating a Reservation for Q While running MRP system should check Unrestricted as well as Project stock and on the basis that should create a PR and also to issue the Materials from unrestricted to Project stock without any transfer posting.

Is there any solution for this requirement.

Thanks,

Muzamil

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Closed.

virendra_pal
Active Contributor
0 Kudos

If Q then standard will only check Project stock

Former Member
0 Kudos

Hi,

I am currently working on batch job to transfer the material from unrestricted to Project stock.

Muzamil

Former Member
0 Kudos

I have a similar requirement. I'd guess that this batch job would look at the project requirements and try to allocate as much 'available' plant stock as possible to the project requirement and adjust the project planned order accordingly.

The job then will 'execute' the allocation - meaning actually transfer the plant stock to project stock.

Any thoughts or comments, if you are still receiving messages from this forum?

Former Member
0 Kudos

Hi,

I have developed a program and it is working fine which will check all the reservations in RESB table and will check the available stock in MARD table and if available transfer the material from plant to project stock by 412 Q.

Muzamil

Makal
Active Contributor
0 Kudos

Hi Muzamil

I don't think it's possible. I think, only ABAP development can solve this.

Lets wait for experts openion on this.