on 11-26-2009 11:50 AM
Hi Experts,
I have a requirement,
FG Code - xxxx, Routing Details - base Qty -100 Pcs in 8 man Hrs, Work Centre Capacity - 8 Hrs Per day, relevent to finite scheduling already tick, lot size fixed. Fixed Order Qty - 100 Pcs,
Total Requirement is 500 Nos. When we run mrp system is giving 5 planned order for 100 Pcs each in same date, but date should be diifferent,
Please help me how to get planned order in different date.
Regards
GR
HI,
Please check the available capacity, in the work center,
you said " 8 Man Hrs"
but how many persons u defined as capacity in work center that would be the out come of total available capacity,
In this case say you have 6 persons working for 18 Hrs a day, available capacity system would calculate as 6*18=108 Hrs
So what you are saying as 8 hrs multiply it by no. of persons you will get the time req. and use this time in routing.
You should get proper scheduling, But criteria is u must use proper formulas in WC capacity and scheduling tab .
And Run MRP with 2 - Lead time scheduling
Regards
Raghu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
What is your scheduling type, if it is backward scheduling, the planned order dates wont change unless falls in past.
and also the i house production time you give in material master plays the role here.
Have you used the formulas in work center in capacity and scheduling tab, the correct one, is a must.
Regards
Raghu
Hi,
MRP does not care about capacity - it assumes that it is there in infinite amounts.
Why don't you look at finite capacity scheduling functionality?
~p
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I guess you need to use distribution key to split your requirements along the time axis evenly or as per function you define.
Reaserch more on how to use the same.
if you are using Rem, you can plan the production in planing table(MF50) and generate the plan orders on required dates.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.