Dear Experts ,
For PO , is it possible to use the account assignment & item category as parameters to device a release strategy ?
I donot see the fields in CEKKO Communication structure .
Pls advice
Regards
anis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Yes you can create PO Relase for Account Assignment & Item Category.
Create characterstics with relevant table name & filed name . or in charactersic values give give the vales and leave the table name & filed name blank.
Try this and let me know any queries.
Thanks & Regards,
smitha