Hi,
I am facing problem after changing the strategy group for a material.
Previously the strategy group for a material was 40. Sale order and schedule agreement were created with strategy 40 and the requirement type in the orders are KSV.
Since we are following Make to stock, and sale orders are not considered for demand planning, we changed the strategy to 10. We entered the demand in MD61 and the PGI for delivery was done for the old orders with requirement type KSV. The demand qty is not reduced after PGI.
We marked the reduction indicator in T.code OVZG for requirement class 50 assigned for requirement type KSV. Even then the PIR quantity is not reduced.
Please provide a solution for this prblem.
With regards,
Afzal.