Hi,
I have a scenario, I have material master set with 04 Inspection type, a Process order is created for this material.
I have made GR in Sto Location 001 for partial quantity and the stocks can be seen in MMBE in Quality Lots and the inspection lot is created.
I have to move the stocks to another Storage location 002 due space constraint through QAC2.
I can see the stocks in MMBE now in 002 storage location in Quality lot.
I made one more GR in Sto Location 001 after some time. I find another inspection lot for the same process order gettting created, which is not desirable.
How to avoid QM Inspection Lot creation at every partial GR for One Process Order.
Many thanks in advance.
Navin