Former Member
Nov 25, 2009 at 10:18 PM

Re: Backward Scheduling in SAP

22 Views

Hello everyone,

I am currently facing an issue for which I dont have the correct logical reasoning.

We have implemented standard Delivery Scheduling in ECC 6.0

I wanted to know the difference between the scheduling done by the system for the 2 materials below:

Item Material Delv Grp Dlv Dat 4 grp Dlvry Date Mat. Avail D Load Date Plant Shp pnt Route

10 Material-1 0 12/02/2009 12/02/2009 11/25/2009 11/30/2009 XXXX 1234 000002

20 Material-2 0 12/02/2009 11/30/2009 11/30/2009 XXXX 1234 000002

Both the materials have the same Shipping Point, Plant, Route

Now since the Material Avail Date = Req. Delv Date - Transit time (2 days int his case) - Loading Time (0 in this case) - Pick Pack Time (5 hrs)

Shipping Point Calender & Route Calender is 5 day Mon thru Friday.

Thus I am not able to understand why the material availability date is different for both the items.

One noticable thins is that item 10 has a 0 stock right now & item 20 has stock.

But I think that should not affect the Delivery Scheduling.

What would be the reason for this behaviour ?

Kindly help me with this behaviour.

Thanks

Vin