PPM has no activities

1. I have material, bom,routing in the R.3

2. IN routing i have maintained the values for the activity but no activity typeshave been assignged.

3. when i try to run the IM i am getting the below error.

Error message:

Material xxx plant 0001 production version V001: PPM has no activities

Message no. U9116

Diagnosis

The PPM could not be created because no activity could be generated from the master data upon which this is based.

The PPM is not transferred.

Any clue how to rectify this would be great!

reg

Dsk

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Nov 26, 2009 at 05:30 AM

    Hi,

    Check following things-:

    1. Correct work center formulas for set up and processing are defined.

    2. Conrol key in routing is scheduling relevant.

    3. At least one standard value parameter (set up or process) is mentioned in routing.

    3. work center used in routing and header and component material is already in active integration model.

    I could not get meaning of " defined standarad values but no activity type assigned" as you mention values for one of activity types only.

    Are you using some customized work center formula containing formula parameters other than standarad. If this is case you need to define those parameters as activities in APO under setting SPRO APO Master data -Production process model -maintain activity types.

    Hope this helps. Confirm back your findings

    Regards,

    Siddharth