Dear All,
I am a little bit confuse with my client requirement about availability check in PP.
For example
01.01.10 Stock 50
02.01.10 OrdRes ProdOrderNumber-01 for 100 PCS
03.01.10 OrdRes ProdOrderNumber-02 for 100 PCS
in ATP system confirm component quantity which is confirm (Prod Order Released) first.
in the example above ProdOrderNumber-01 can be confirmed only for 50 PCS (50 PCS can not be confirmed)
the case is sometimes user will forget to confirm the remaining qty of 50 PCS of ProdOrderNumber 50 PCS when
next MIGO 100 PCS posted, so the 100 PCS is comfirmed for ProdOrderNumber-02.
in fact, in chronological of date it is impossible. The MIGO 100 PCS should be allocated to the earliest order first.
This is all can be happened because ATP confirm qty (First in First out without considering component requirement date) !
Can i configured ATP that is not confirmed, but only check availibility of requirement in chronological requirement date?
or same logic as availability check in MD04 ...
any other idea / suggusted ?
Best regards,
Freddy Ha