ppds external operation

92 Views

Dear Friends,

In our scenario, we are mentioning control key pp02 in routing for external operation. this facilitates APO to schedule external operation. we are mentioning the value of pp02 in routing as 5 days.that is the time taken to process the external operation.

now the problem is, APo is considering 5 days only if the external operation is after first operation. but if i make the first operation as external operation then it is multiplying the no. of days we define into 4 times. that is for 5 days it is scheduling for 20 days. So is there any setting.

Pls help

Vinay