Hi

I have created routing without any material assignment.

I have used it in production version of one material.

When i try to create planned order for that material then during scheduling it says that material does not have routing.

Accepted Solutions (1)

Accepted Solutions (1)

former_member207022
Active Contributor
0 Kudos

Dear

You have to maintain material in routing. Go to routing header and click material assignment, enter group say as 1 and your finished material code.

former_member240058
Participant
0 Kudos

Hi Ganesh

Though we are putting group number in production version details, then also we have to put material number in material assignment.

former_member207022
Active Contributor
0 Kudos

Yes you need to put the material number and try. It will work for you.

former_member196398
Active Contributor
0 Kudos

>

> Hi Ganesh

>

> Though we are putting group number in production version details, then also we have to put material number in material assignment.

Mayuresh,

If you check the production version, it would give you error saying that Routing is not valid. You need to have the routing assigned to the material through material assignment and then use in the Production version.

Regards,

Prasobh

Anupam1143
Active Contributor
0 Kudos

HI Prasobh

Congrats on achieving the milestone of 10K.

Its an impetus for us to do better

Congrats a ton

Best Regards

Anupam Sharma

former_member240058
Participant
0 Kudos

Hi Prasaobh

Though i have done material assignment in routing then also iam getting red status check.

Former Member
0 Kudos

Hi

Please check valid dates and Lot size of routing.

Regards,

srihari.M

Former Member
0 Kudos

Dear Mayuresh,

1) As you assigned Components in Routing still the valid & changed dates will be seen in headers data

2) so as per PV dates, still Routing will not have valid components

3) Go to CA02 there is a key date option change this date to before PV date & save

4) then do the consistence check in PV

Regards

Madhu

Former Member
0 Kudos

mayuresh,

make sure you are entering routing at correct position in prod version.

you have 3 options; detailed/rate based/rough cut. enter accordingly.

Answers (2)

Answers (2)

former_member522307
Participant
0 Kudos

Mayuresh,

Check the Status in Header Detail, ensure its Released.

Thank you,

mk

Former Member
0 Kudos

Hi,

Whenever a production version is created, consistency check should be carried out.

In your scenario the production version created will show error if you run consistency check.

It is mandatory for you to assign the material in the material assignment tab in the routing header.

First assign the material in the routing and check the consistency in production version.

Hope above clears your doubts

Regards

Suri