We are facing great difficulty in the SAP Scheduling users in the software adoption when it comes to scheduling.
As the users wants the scheduling in the MSP or Primavera which they find it to be user friendly and the dates calculation the time varinace is easy.
However SAP has some rigidity in the netwrok dates and the WBS dates.
I want to know from all the consultant community whether people in the EC & O domian are sticking to only SAP for scheduling or they have an itermediate such as MSP or primavera for the scheduling purposed.
Its my personnel opinion which may be correct or wrong but SAP is unable to meet the scheduling requiremnets of the projects and maintaining the relationships of 1000 + activities is difficult as well as what if scenerio.
Please suggest what are your observations!!