Hi Experts

I use CJ30 for original budget proposal by project manager and CJ32 for release by Top Management.

Once after allocation of budget using transaction CJ30, subsequent additions or deletions shall be carried out using budget updates only (suppliment, return, transfer) etc.

But still i am able to edit in CJ30. Is there any setting to make the values uneditable for a wbs for which the original budget is released.

warm regards

ramSiva

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

you can use user status to lock the original budget once the budget is realesed. Create user status with business transactional control Budgeting disallowed.

regards,

Rahul