Hello,

In normal correction (SDMJ) workflow, the action Confirm Successful Test is selected in the Development with Release phase of a project/maintenance cycle. The status of the Change document changes to Consolidated after that, and you then be able to move the cycle to Test phase.

How can we customise the standard workflow so that Confirm Successful Test is selected in the Test phase? This seems to make better sense.

I'd appreciate any help from any one of you who have done some customising to the SDMJ standard workflow. Many thanks in advance for your help.

BR Li

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Nov 23, 2009 at 11:39 AM

    Hi Li,

    I had the same dscussion with my customers more than once, it is hard to understand to perform the action "Confirm Successful Test" before Test phase.

    You could add another status to SDMJ (or a copy of SDMJ, for instance ZDMJ) before Consolidated.

    But we selected another option, by using test messages during test phase and therefore following SAP standard process. So, a developer confirms successful integration/unit testing after he finished his development/customizing activities in dev by changing the status to consolidated.

    If some issues are detected in Test phase, we are using test messages to correct it. But you are right, at the end of test phase there is no additional status which says: all is fine, go ahead and move it to production. Only be checking that all Test messages are finished, the Production transport approver can be sure, all issues have been resolved.

    But by adding another status, please consider this: You have to create a copy of SDMJ (ZDMJ). After this, all enhancements and changes to SDMJ delivered by SAP, you have to do manually for your new transaction type ZDMJ, otherwise you will not get the functionality. That's why I'd recommend to use SDMJ as delivered by SAP and also use Test messages during test phase.

    Best Regards,

    Holger Slomka

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Li,

      I had same discussions with SAP. SAP's recommendation always to move changes into production is not really possible under all circumstances. Our approach in such cases is to undo changes in Dev, and to remove transport requests from production import queue manually and then to withdraw the normal correction.

      Not the best approach, and it requires a lot of manual effort.

      Best Regards,

      Holger