cost plan for sim version

Hi experts

The business requirement is as follows:

1) Project schedule option-1 with work packages and costing plan ( L1 schedule)

2) Project schedule option-2 with different work packages and relevant costing plan (L2 schedule)

Clien requires both of these as drafts

The requirement can be met by creating sim_ver1 and sim_ver2 in transaction CJV1 (with out having operative version).

Subsequently the approved sim version will be used for creating operative version.

But is it possible to maintain cost plan for sim versions?

If no, please suggest best practice.

warm regards

ramSiva

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Nov 19, 2009 at 07:46 AM

    You can only use network costing for simulation version. Other cost planning methods are not possible for simualtion version. Refer SAP Help