Hi Gurus,
I would like to know whether the Secondary Resources in Master Recipe will be considered in Capacity Planning / Evaluation.
I have created a resource with Resource Category Proc. unit/Stor.res (Category 15 )resource.
Now whenever I try to check the Capacity Evaluation using CM50 / CM52 , the Rem.cap.reqs is always Zero, whatever amount of Process Order I have created, and the Avail.capacity and Rem. avail. capacity, are never reduced.
Thanks and Regards,
A S K