Budget checking for services with "Unlilmited" indicator set

hi friends,

Under normal cases, the budget checking is happening properly for the services in a project.

But I have certain service activities where I require to set the "Unlimited" indicator set (in the service specification screen)and some other services where I set a value limit to the unplanned services (in the Limit section of the service specification screen).

In these cases, the budget checking is not happening as expected by the standard methods. Please note that the availability control is active.

Please help me out.

regards

Pratap.V

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Nov 19, 2009 at 06:09 AM

    Please check this note .

    Note 46209 - No availability control for goods receipts

    447102 - Availability control messages for goods movements

    With Regards

    Nitin P.

    Add comment
    10|10000 characters needed characters exceeded

    • Just check with Exit, But I doubt, whether it will consider unplanned values.

      That exit is meant for to check budget at time of GR ( say your GR values is 12000 and PO Commitment is 10000 so, it will check additional 2000 while doing GR )

      This what I mean note is suggesting use of Exit to trigger availability control at time of GR.

      With Regards

      Nitin P.