Individual/Collective Requirement indicator in MTS

Hi Gurus,

Can you please let me know what is the relevence of individual/Colelctive Requirement indicator from MRP4 view of material..

for Finished product as well as its sub assembliees in case of make to Stock planing strategies.

i know how it works in MTO and how depednent requirements can be grouped together or sepated based on this indicator.

When i tested the same in case of MTS, i found for dfinished product as well as sub assemblies behaviour is always like collective irrespective of MRP4 indicator.

any thougts lets me know.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Nov 18, 2009 at 08:39 AM

    Dear Santhosh,

    MRP-4 as 1 : In individual planning, this indicator is used to display the dependent requirements of a component separately.

    MRP-4 as 2 : In collective requirements, this indicator is used to display the dependent requirements of a component grouped together.

    This Indicator is useful to control the planning of dependent requirements if the main product is being planned with strategy 20 ie; MTO Process.

    Ramagiri

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Nov 18, 2009 at 08:01 AM

    Dear Santosh,

    As per my knowledge this indicator plays a major role only in MTO

    Coming to MTS, this indicator will not play any role

    it's one & same i you input 1 or 2 in MTS

    Regards

    Madhu

    Add comment
    10|10000 characters needed characters exceeded

  • Nov 18, 2009 at 08:04 AM

    Dear,

    Individual collective indicator is only for MTO strategies

    For MTS it has no role all materials and dependent requirements will be procured collectively.

    Check this link,

    individualcollective-requirements

    Regards,

    R.Brahmankar