we have a mesure on process ordem with status TECO and day by day is necessary to run a report to analyze the dates of orders that was final confirmed and change status to TECO and comparing the base schedulle dates to real dates final confirmed.

Anybody has option to be selected and showed up on CM03 these status orders like TECO status?

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Itamar

This is not possible in the stnadard system.

Capacity reports, such as CM03 and CM07, are based in the capacity requirements, which are stored in table KBED. Once you complete an order technically, those capacity requirements are deleted, so that the completed order won't allocate capacity anymore.

It is not possible, in the standard, to avoid the deletion of those records when completing the order.

Regards,

Caetano

Answers (1)

Answers (1)

itamar_doprado
Explorer
0 Kudos

Thanks Caetano

Your information helped a lot to my decision.