I am running the activity "Calculate Access Plans (Simulation) (Optional)" and takes and takes a long time. It has given me 2 errors. My questions are:

1. I have to correct the errors and re-run, although the activity is "Optional"?

2. If I run the activity, will take a long time or just take the time it runs for these 2 errors?

Thanks

Hugo.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Thanks.

Former Member
0 Kudos

Hi Hugo,

1. Now since you have chosen to the size prediction you will have to correct the errors and run the optional step also. However if knowing the amount of data that will be transferred to receiver system is not improrant then you can skip these steps. If so you will have to raise a OSS message. Support colleagues will help you to skip the steps.

2. The access plan will happen only for the errored out objects and not for all objects

Regards

Raghuram