I have configured overhead through OPL1 and KSAZ.I have defined two overhead in cost sheet:1)Material overhead and 2)Manufacturing overhead.

In Material overhead,i have defined all materials cost element in "Base".Then in "Ovehead rate" i have defined overhead % for overhead type 1 & 2.Then in "Credit" ,i have defined,secondary cost element(category41).

Same process i have followed for "Manufacturing overhead" also.

In KSAZ,i have defined same process.

Now while i run KGI2 for a particular production order,i have seen that overhead is calculated on "Manufacturing Variance-Finished Goods".My question is why it is not calculated on Material .