Former Member

Purchase order in the backend system

hello all,

we are using SRM 7.0, classic scenario.

we are implementing BBP_CREATE_BE_PO_NEW BAdI to change some data that is transferred to the backend for the purchase order creation.

i tried to set external breakpoint for wf-batch. however, it seems that this BAdI is not being called.

i also tried implementing BBP_DOC_CHANGE_BADI, but still this BAdI is not being called during PO creation.

would you know what BAdI to implement to change the data that is transferred in ERP for the creation of purchase order?

regards,

kezia

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Nov 17, 2009 at 12:56 PM

    Hi,

    The PO created in the background is performed in BAPI_PO_CREATE or BAPI_PO_CREATE1 in R/3 system , so probably you have to set the brakepoint in the back ground and to check all imported parameters there not in SRM system.

    Regards,

    Desislava

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member muthuraman govindasamy

      hello muthu,

      can you confirm that BBP_PO_INBOUND is only used for extended classic scenario?

      i am confused why this function module is being called when we did not activate extended classic scenario.

      i tried setting a breakpoint in META_BAPI_DISPATCH, unfortunately it is not stopping there.

      would you know any FM in SRM that calls this BBP_PO_INBOUND function module aside from B46B_DPO_TRANSFER as this FM is triggered only when ECS is active?

      many thanks,

      kezia