Hi Gurus,
After MRP run for a material ( there is a dependent requirement for the material), when i am displying MD04, i am getting the planned order first(with corresponding available stock) and then in the next line dependent requirement(with available stock 0).
But actually it should show dep. requirement first and then the planned order.
Can you please tell how can i get the screen(MD04) properly? is there any settings for this? i am getting this only for one material.
Regards
Rajib Pathak