Dear All,
I am using 4 activity types i.e. POWER/MACHINE/STEAM/LABOUR.
MACHINE & LABOUR are calculated using same formula: like
Machine=machine*(SAP_09/SAP_08)
Labour=Labour*(SAP_09/SAP_08)
& for POWER & STEAM I am using:
Power=(Power(machine(SAP_09/SAP_08)))
Steam=(Steamr(machine(SAP_09/SAP_08)))
But on seeing the lof for cost while creating a process Order I am getting only the machine & labour correct,The steam & Power are getting calculated wrongly.
For example
If my base SAP_08=1200000
& SAP_09=1200000
& my activity values in the recipe =
Machine= 16 Hr
Labour= 64 hr
Steam= 127 Kg/Hr
Power=388 KW
Please advice how to resolve this issue.