Easy Cost Planning

219 Views

Hello All

In Easy cost Planning we want to take the cost of one of the WBS elements and multipy the same with 2% or 3 %.

How we can make a entry field for WBS element in the easy cost planning forms.?

Business scenario - in the given WBS structure we have, 1. Engineering, 2. Construction, 3. Procurement WBS elements now the we want Project Managment cost as a percentage of engg cost + % of Construction cost + % Procurement cost

How we can achieve the same.

We could create a planning form and in the we can enter % like 2 %, but the object field we are not able to create in the form

Thanks for the help in advance...

Srihari.G