I want to record working times on a WBS-element without netword and activity.

As I do not want to plan the activity, (I only want to collect the workind time on some WBS-elements), I want to allocate persons to a WBS-element, and I want to record working times in e. g. Tcode CAT2.

But I can not see how to allocate persons to a WBS-element, and then record working times on the person.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

In addition to what Nitin has commented you can also refer the following thread,

http://help.sap.com/saphelp_47x200/helpdata/en/f1/76a97879a311d38e720000e81de309/frameset.htm

Hope this provides you with some info.

Regards,

Gokul

Former Member
0 Kudos

Hi,

As far as i know standard SAP does not have this feature of recording working times against a WBS. You can do it only against an activity since you give the necessary details like Work Center, Work and activity type in the activity. Also you can maintain project team for a WBS element but then you have to go CMP2 and then assign these resource to the respective activities in order to record the working times.

This is what my understanding is. Lets wait for experts to reply on this.

Best Regards,

Gokul

nitin_patoliya
Active Contributor
0 Kudos

SAP supports the time recording against WBS as well as Network activity. Most of time time recording is done against Network activity as the gokul has pointed out the advantages. But You can configure the same for the WBS element as well. Process is almost similar for the configuration.

You have to create relevant Data Entry profile, in filed selection you have to select Receiver WBS as input field & Activity type as input filed along with other required input filed.

After CAT2 postings , you need to run CAT7 instead of CAT5.

Revert back if you face any problem.

With Regards