on 11-13-2009 7:04 AM
Hi! All,
In CJ20N, I have created a project with WBS elements & activities. Once I release the project I can see the Project Cost Plan column is having some costs. From where the system is picking up the Project Cost Plan.
Best Regards
OK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Sorry, to give more clarification..When we open the Project Planning Board we can see the Projct Cost Plan column which is showing some cost. From where it is coming?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
That cost is coming because you would have maintained some activities which in turn would be having a work center and activity type assigned to it. There is a rate maintained for this activity type in KP26. System calculates the cost based on the rates maintained in KP26.
Also if you have some planned in the project system will display the cost for these matl components also.
Regards,
Gokul
there is also the planning profile for projects which has the costing variant
and the network parameters which have the costing variants for networks
the costing variant has a valuation variant
it is the valuation variant that decides where to get the cost from
e.e if work defined then use activity pricing
if material componenet added then use standard price from materila master etc