Skip to Content
author's profile photo Former Member
Former Member

Data Cache usage > 96%

Hi Experts,

With total 7 planning versions and total size of 9GB, the data cache is constantly filling up

Total 14GB allocated and each time we create a new version the usage goes up by 10%.

There are no old sessions more than 4 hrs and when 5 planners starts working simutaneously, the cache starts filling up

Thanks,

Naren

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Posted on Nov 13, 2009 at 08:36 AM

    > With total 7 planning versions and total size of 9GB, the data cache is constantly filling up

    >

    > Total 14GB allocated and each time we create a new version the usage goes up by 10%.

    >

    > There are no old sessions more than 4 hrs and when 5 planners starts working simutaneously, the cache starts filling up

    Now what?

    You create multiple versions of liveCache objects in parallel - of course the cache usage will increase (and also the used space in the data area).

    That's how the multi-version-data-handling works.

    A copy of the current version is created for each new version.

    So either add more cache, reduce your planning version complexity/size or do less in parallel if you want to prevent the cache from beeing used 100%.

    regards,

    Lars

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.