Hi,

I'm working on an existing environnement in a new customer and they have three systems : Dev, Int, prod

On the Integration system i can not execute RSPCM transaction (it takes very long time).

it take times because it check table in ECC so i need to archive data. but this is not the unique problem.

When i execute the RSPCM transaction in BW integration system, i don't have the pop up with the time restiction :

Today

Yesterday - Today

....

I don't know how to display this pop up bu default. On dev and prod system i have this popup each time.

Thanks for your ideas !!

Cyril

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

I found the problem myself. the question is due to process chain never executed. for the other chains this is always the last execution status.

Former Member
0 Kudos

Hi

when you execute the RSPCM it looks at logs that you ask in the popup. it displays the last status. withot this selection the logs check can take long time because it checks lots of table even in source systems.

that's why i need to fuse this filter.

Regards

Cyril

former_member200211
Active Participant
0 Kudos

hello,

As far as I know, in RSPCM when you click on any Process Chain it will display a day or two's. You can get the pop for displaying logs of other days, using the "Other Logs" option available in the same screen at the top.

Regards