Hello Gurus,
I'm trying to implement Project with customer functionality in Project System Module integrated to CO-PA.
As an example, i created a sales order with several billing items to different material codes and assigned to a single WBS, in this case, my main problem is how to have information off billed product to WBS in CO-PA.
I tried to use result analysis in Project System, but system settle information in one single line to CO-PA without the product characteristic fulfilled. How I could have information in CO-PA off revenue, and cost of sales by product and project without posting sales document directly do CO-PA?
I posted a billing (account assignment to WBS) document to WBS to have cash management information by Project (WBS), (i have activated PS-Cash functionality), in other way i couldnu2019t have this information in documents that results from billing documents.
My first tentative to solve this issue, was to post WBS and profitability segment at same time in sales order, but system issued an error message. In this situation i here trying to apply a system concept that exists in CO, internal order posted at same time to cost center, one is posted as statically value and other is real value.
regards
Jleal