Hi Guys,

I am not able to close a project, the error message thrown out is KO450, "There is still WIP in WBS". Any idea how to fix this issue. please let me know if you need more details.

Regards,

Paval.

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Nov 11, 2009 at 06:57 AM

    This message was moderated.

    Add comment
    10|10000 characters needed characters exceeded

  • Nov 11, 2009 at 04:21 PM

    Check for any open PR, PO, MO, etc. with open GR or IV.

    Take a look at the following notes.

    [SAP Note 176222 - KO450 resetting account assignment indicator in WBS elemnt|https://websmp206.sap-ag.de/~form/handler?_APP=01100107900000000342&_EVENT=REDIR&_NNUM=176222&_NLANG=E]

    and

    [SAP Note 421710- Check report whether "Deletion flag" status can be set|https://websmp206.sap-ag.de/~form/handler?_APP=01100107900000000342&_EVENT=REDIR&_NNUM=421710&_NLANG=E] This one is probably the best.

    If these do not apply, search SDN.

    Regards.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 14, 2010 at 01:58 PM

    Hi Paval,

    Firstly, please use RKACSHOW to have a look at table COSBA which will

    show that WIP still exists against the WBS Element.

    If you can archive the order with the balance, change the indicator

    in the settlement profile from 'To be settled in full' to 'Can be

    settled' or 'Not for settlement'. (settlement profile in SPRO ->

    Product Cost Controlling -> Cost Object Controlling -> Product Cost by

    Period -> Period-End Closing -> Settlement -> Create Settlement Profile)

    As a result, there is no check as to whether the balance of the sender

    is equal to zero when you archive the sender. Try and close the project

    after doing this.

    Please remember to reset the 'To be settled in Full' in your settlement

    profile after this. Try this first to see if you can close

    the order but please remember to reset 'To be settled in full'.

    You can also use program COPCOBJ_REORGCHECK from note

    421710 to see what values are preventing the order from being closed.

    You can then proceed according to note 140672 or note 421376, depending

    on which note better suits your particular circumstances.

    Then, If you maintain the customizing you can execute results

    analysis to cancel the WIP and settle to cancel the WIP also in FI,

    you will be able to close the wbs element.

    Please review notes 76354 and 172355 too.

    Thanks a lot and kind regards,

    Enrique Sosa