Hi Gurus,

What is line balancing?

Where it comes in REM?

I need to make a small demo on it.

Can anyone help me on this.

Srini

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Nov 10, 2009 at 11:11 AM

    Hi

    check the notes:

    Process Line Balances

    Prerequisites

    You must not have selected the indicator No line balancing in the initial screen for the line hierarchy.

    You must have created one or more rate routings for the materials you want to produce.

    You must have entered the rate routing (or standard routing) in the production version in the material master.

    Procedure

    Starting from the main Line Design menu, choose Line balance ® Create.

    The system displays the initial screen for line balancing.

    Enter the following data:

    the plant

    the line hierarchy, for which you would like to create the line balance

    the version number of the line balance, which you are free to choose

    the validity period or a change number

    You can no longer subsequently change the Valid from date.

    Choose whether the system should select the materials via the production version or via an existing version of the line balance.

    Choose Enter.

    The system selects the materials that you can manufacture on the production line and displays these in the table on the tab page Material. If you have entered more than one production version in the validity period for a material, then a dialog box will appear, in which you can select the desired production version.

    The number of takts and individual capacities entered in the line balance is only valid for the current line balancing version. However, if you are planning a new production line and would like to determine the necessary number of takts and individual capacities using the line balance, then you can transfer these entries into the line hierarchy. To do so select the indicator Max.line balancing.

    check the link:

    http://help.sap.com/saphelp_470/helpdata/en/5a/749c86ee5b11d1b5c30000e82d81c3/frameset.htm

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.