on 11-10-2009 7:28 AM
Hi,
I have a scenario in which , I am using trigger point in opertaion 0010 to generate a new operation lets say 0012(rework operation).
Now in opaertaion 0010 ,I have confirmed 6 out of 10 quantities and sent 4 for rework.In operation 0012,which is rework operation,I confirm 4 quantities (rework quantity).
Now i want to confirm total 10 quantities in operation 0020 but I am not able to do it.
Following error is coming " Up until now only 4 EA confirmed for predecessors 0012"
pls guide.
Settings in "Define Confirmation Parameters " are - Warning when over delivery tolerance exceeded , Warning for under delivery.
thanks to all..
Problem solved
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Madhava,
Taking the above example.
I have a scenario in which , I am using trigger point in opertaion 0010 to generate a new operation lets say 0012(rework operation).
Now in opaertaion 0010 ,I have confirmed 6 out of 10 quantities and sent 4 for rework.In operation 0012,which is rework operation,I confirm 4 quantities (rework quantity).
Now i want to confirm total 10 quantities in operation 0020 but I am not able to do it.
Following error is coming " Up until now only 4 EA confirmed for predecessors 0012"
Solution used--in operation 0012(rework) i confirmed 4 quantities and also confirmed the activities corresponding to them.
After that i confirmed 6 quantities for operation 0012 but without any activity confirmation as these 6 are not rework quantities.
Now in operation 0020,I am able to confirm 10 quantities as wanted.
Hope this helps.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.