How to configure Reserves Settings in WIP-Result Analysis Key

Hi,

I need to Capitalize the un-realized revenues/Cost?. I came to know that it can be fixed by doing configuration in Result Analysis Key. What are the settings that i need to do in WIP configuraion (Product Costing). Kindy help me or provide me some inputs to full fill this requirement.

Thanks

Kishore

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Nov 10, 2009 at 11:41 AM

    Use Tcode OKG5 - Assign the required Cost elemnets to a Line ID, under "Req To Cap" coloum.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.