I need to install Process Control 3. i would like to know if i need to install ABAP and JAVA as add on or install JAVA as central system?

Thanks

Sigal

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Nov 09, 2009 at 08:32 AM

    Hi,

    are you asking if a single or dual stack (add-in) installation is "better"?

    There are two main disadvantages when using a dual stack Java/ABAP system:

    -UME needs to be connected to ABAP (can cause some issues)

    -sizing only "symmetrical" (e.g. cannot add just one Java instance)

    Advantage is you do not have to change/synchronize passwords on both systems...

    Cheers,

    Dominic

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 06, 2010 at 09:51 PM

    The process control3.0 installation is at two levels : PC3.0 core components & PC3.0 Portal Business packages.

    1) PC3.0 Core component installation is on SAP NW ABAP 7.01 EHP1 SP03 or above

    2) SAP Portal is the new UI and available on the JAVA stack. The PC3.0 Portal Business Packages need to be deployed here.

    3) PC RTA to be installed in the ERP system (optional : based on use of automated monitoring)

    You can have it as ABAP+JAVA stack or have them separately stacks as per your organization policy.