Skip to Content
0
Former Member
Nov 06, 2009 at 04:32 PM

FI/CO integration - WBS name

42 Views

Hi there;

I set-up integration between cProject and FI/CO with PS structure automatic creation after change status (set status "to transferred").

It work well in general, but there is something strange about wbs element code.

Infact, I change cproject project phase number with my own code; ps wbs element don't take this number but the first original number from cProject phase (eg. 19000000000000001542009).

Is this an error or it's normal?

Thanks a lot

Ciao