Hi Experts
I wish to use this functionality for the following scenario:
Project material needs long delivery duration. And the delivery monitoring is critical function since any delay hampers entire project.
Especially, for major project items, the release of purchase order is not enough. Because subsequently there are several activcities need to be performed by both parties, delay in which will impact the original delivery.
So, i wish to have the events as shown below:
Z0001 Receipt of acceptance
Z0002 Receipt of Advance Bank Guarantee doc
Z0003 Release of Advance
Z0004 Receipt of Drawings
Z0005 Approval of Drawings
My query is, what is the aspect with Refernece dates.
What is baseline, plan, actual. How the dates can be linked?
I request experts to guide me in this regard.
warm regards
ramSiva