Skip to Content
0
Former Member
Nov 06, 2009 at 02:12 PM

Monitoring mateiral dates functionality in PS

91 Views

Hi Experts

I wish to use this functionality for the following scenario:

Project material needs long delivery duration. And the delivery monitoring is critical function since any delay hampers entire project.

Especially, for major project items, the release of purchase order is not enough. Because subsequently there are several activcities need to be performed by both parties, delay in which will impact the original delivery.

So, i wish to have the events as shown below:

Z0001 Receipt of acceptance

Z0002 Receipt of Advance Bank Guarantee doc

Z0003 Release of Advance

Z0004 Receipt of Drawings

Z0005 Approval of Drawings

My query is, what is the aspect with Refernece dates.

What is baseline, plan, actual. How the dates can be linked?

I request experts to guide me in this regard.

warm regards

ramSiva