PM Order scheduling user exit

We want to change the proposed scheduling dates of the work order. Standard SAP does not do what we want. Is there a user exit we can use?

To explain a bit more what we want to do is the following:

We have a work center with capacity 8 hours. We create one order with planned hours = 4. Scheduled order start time is 09:00 and end time is 13:00.

We create a second order again with 4 hours for the same work center. System again proposes 09:00 - 13:00 whereas we want to change that to 13:00 - 17:00.

thanks in advance

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Nov 22, 2016 at 12:32 PM

    Hello, Michail.

    Maybe for you will be useful user-exit IPRM0002, which determine planned dates for maintenance plan.

    Add comment
    10|10000 characters needed characters exceeded

  • Nov 22, 2016 at 12:54 PM

    Michail

    How would the second order "know" about the first order?

    This can be achieved manually in standard via the operation Relationships. Simply make the first operation in order 2 related to the last operation in order 1 (assuming the standard FS relationship between operations).

    PeteA

    Add comment