PM Order scheduling user exit

Nov 22, 2016 at 09:55 AM

107

avatar image
Former Member

We want to change the proposed scheduling dates of the work order. Standard SAP does not do what we want. Is there a user exit we can use?

To explain a bit more what we want to do is the following:

We have a work center with capacity 8 hours. We create one order with planned hours = 4. Scheduled order start time is 09:00 and end time is 13:00.

We create a second order again with 4 hours for the same work center. System again proposes 09:00 - 13:00 whereas we want to change that to 13:00 - 17:00.

thanks in advance

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Yauheni Sarachynski Nov 22, 2016 at 12:32 PM
0

Hello, Michail.

Maybe for you will be useful user-exit IPRM0002, which determine planned dates for maintenance plan.

Share
10 |10000 characters needed characters left characters exceeded
Peter Atkin Nov 22, 2016 at 12:54 PM
0

Michail

How would the second order "know" about the first order?

This can be achieved manually in standard via the operation Relationships. Simply make the first operation in order 2 related to the last operation in order 1 (assuming the standard FS relationship between operations).

PeteA