Problem in usage decision if posting to Return delivery

Hello

when we are doing GR against outline agreemnet for example 5 quantity(5 seperate line item during MIGO) automatic inspection lot is getting created(only one inspection lot is created for quantity).

Now the problem is while doing Usage decision through QA11 if for example 2 quantiy is posted to return delivery and 3 to unrestricted use the system is giving error message "2.00 PCE incorrect Deficit of PU GR quantity 1.00 PCE".

The reason for that is

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Nov 04, 2009 at 03:20 PM

    cont....

    The reason for that is the GR document has 5 seperate line items with 1 quantity each so the posting to Return delivery is 2 quantity,

    so please advice any setting in configuration required to allow the QA11 with more then 1 quantity to "return delivery" even though the GR docuemnt has line items with 1 quantity each.

    Thanks for your reply.

    Regards

    Santosh

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Try to post UD for 5 times (QA11 and then QA12)...3 times posting into Un-Restricted Stock and 2 times into Return Delivery because for each of GR Line Item Material Document has been created separately.

      Best Regards,

      K. Raghavendra Nayak

  • avatar image
    Former Member
    Nov 04, 2009 at 05:45 PM

    Hi

    can you not use one inspection lot per line item.

    check the setting in Inspection type.

    This will create multiple inspection lot with reference to multiple line items.

    I hope this will add some value

    Regards'