settings to trigger output at the time of PGI in shipment

Dear Friends,

I have a requirement where an output has to be triggered from the shipment document (VT02N), when the post goods issue is completed.i.e when the user completes the "shipment start" stage in the shipment document.

The output document has to be sent by email to a couple of users when PGI is completed in the shipment.

Since,here we are not manually triggering the output, instead the output is triggerred automatically when PGI is done.

Please let me know the settings to trigger a particular output when PGI is done.

Waiting for valubale feedback.

Regards,

Sampath

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Nov 09, 2009 at 06:51 PM

    Hello,

    You can do this through Configuration.

    LE>Transportation> Shipments >Define and assign activity profile

    With reference to shipment type you have 7 status available. In your case Shipment begin stage you can Set PGI and Output trigger by creating variant.

    All you have to do is put the mouse on the "at shipment begin" and select maintain and you can see the PGI option and output fields where you can call the output type there.

    try it will work....

    tkreddy

    Edited by: Tkreddy on Nov 10, 2009 3:00 AM

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Nov 25, 2009 at 07:14 AM

    answered