We maintained safety time in MRP settings . We are pointing another plan for manufacturing .

If we receive the demand management VSF - two weeks later , as we maintained the safety time as 10 days . we are expecting MRP should recommend to produce the product 10 days in advance and it should deliver the product from the manufacturing plant . But safety days is not influencing , the safety indicator is 2 ..MRP type PD / and lot size is weekly .. What is the missing date here ?

Any input will be highly appreciated