Former Member
Nov 02, 2009 at 01:12 PM

Planned order date mismatch between R/3 & APO

129 Views

Hi,

We are using set up time from set up matrix in APO. Set up time are getting considered correctly in APO but in R/3 start date starts from Process activity start date. Sequence dependent set up is ignored completly in R/3. When I convert planned order to production order from APO by setting conversion indicator then date are correct. In Production order set up time from APO is considered in R/3 too.

We have defined set up group in APO. Set up matrix in APO . We have not defined corresponding set up group category in R/3. After tranfereing PPM from R/3 to APO . We assign set up group manually in APO.

Can anybody suggest possible reason for this mismatch.

Regards,

Siddharth