HI,

Please let me know in the extended classic scenario when the PO is created in SRM does the same PO number gets created in the backend system.Also is the PO created in the Backend system can be opened in transaction ME21N or it can be viewed only in ME22N transaction.

Thanks,

Manu

Accepted Solutions (0)

Answers (5)

Answers (5)

former_member183819
Active Contributor
0 Kudos

Hi

you must get same no range i both environments.

tellus what is the exact problem and no difference you are getting.

br

muthu

Former Member
0 Kudos

Yes, PO in SRM has same number as R/3, and can only be viewed (readonly) in ME23N. Number range must be set as external assignment. in R/3.

0 Kudos

While configuring consultant has to maintain the same number range in both systems. This way the PO number created in SRM system remains the same as in backend ECC system.

This PO is only readable in backend system. Only ME23.. transactions can be used to view this. If user is allowed to modiify this PO in backend system it will lead to inconsistency between the systems.

Former Member
0 Kudos

Hi Manu,

Same PO number gets created in the backend system and it can be viewed only in ME22N transaction.

Regards,

Neelima

Former Member
0 Kudos

Hello,

Yes, In Extended calssic scenario, the same PO number replicated to Backend. But, this po is not modificable. You can see through ME23n.