Hi All,

While creating the Period Split Profile at the time of saving "no time series maintained" error is appearing.

Regards

Sumit

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Nov 02, 2009 at 11:23 AM

    Hi Sumit,

    Before maintaining the period split profile, maintaining the distribution

    function is mandatory.

    Distribution function will be maintained using transaction

    /SAPAPO/DFCT.

    Under this, ensure that the length of distribution period (ie

    the time series period) and the distribution function values

    are maintained.

    Upon maintaining this, then try creating the period split

    profile

    Please let me know if still any issues

    Regards

    R. Senthil Mareeswaran.

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Senthil,

      What should be the distribution function values?

      I don't know what to give the values in it.

      I read somewhere in the sap notes that we give weighting factor but how to determine what should be the weighting factor.

      My requirement is data is there in period in DP and I have to send it to R/3 in weeks so I need to use the Transfer Profile where in I will have to give the period split profile.

      Please help me.

      Rgds,

      Prabhat

  • author's profile photo Former Member
    Former Member
    Posted on Nov 02, 2009 at 10:01 AM

    Hi Sumit,

    1) Check whether you have specified which storage buckets profile is to be used for the release to SNP. This storage buckets profile must contain days only.

    2) Check whether time series is maintained before creating this profile

    Regards

    R. Senthil Mareeswaran.

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Senthill,

      I am maintaining the Period Split Profile separately through SDP_SPLIT, as i have not linked this period split profile with any planning area yet then how will i am getting the time series error?

      Needs your valuable input

      Regards

      Sumit Kalyan

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.