Hi Experts
As per PLM210 (Page 103)m "Simulation versions are edited using the project planning board or - as of SAP R/3 4.6C - using the Project Builder".
But I could not open simulation version in Project Builder or PPB.
Is there any setting need to be done to achieve this?
Warm regards
ramSiva
in project builder
go to settings -> options
tick simulations
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you Virendra
Can you guide me in creating opertative project P-1234 from simulation version P-1234/SIM001
Similarly creating simulatiion version P-1234/SIM002 from operative project P-1234
Let me know whether I can carry out these processes in PB or to go for CJV* Transactions?
warm regards
ramSiva
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.