Table for planned cost

Hi All

In which Table and field can i find planned costs for maintenance order. I need this info for individual orders and not collective planned costs.

Thanx in advance.

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Nov 02, 2009 at 04:18 AM

    Ruhail,

    You should be able to get that from table PMCO. It holds the cost for the order at the Value category level. You would have to sum up the cost from different value categories to arrive at the total planned cost of the order. The estimate and actual cost at the value category level is also available from the same table.

    The same information can also be obtained from the controlling tables of COSS,COSP and COEP.

    Regards

    Narasimhan

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Nov 02, 2009 at 04:19 AM

    Hi,Ruhail,

    Please check PMCO3

    Thanks,

    Rahul

    Edited by: Rahul Pawar on Nov 2, 2009 5:24 AM

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Nov 02, 2009 at 11:44 AM
    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.