Hi all,

There is some inconsistency in the PS reports.Actual overall is coming in the S_ALR_*87013558 at the network level.But it is not summing up at the WBS level i.e cost at network i s 50000 INR ,but at corresponding WBS,it is coming up as 0 INR.What could be the reason behind this?

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    Nov 01, 2009 at 11:10 AM

    Try running CJEN and then see the report.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Nov 27, 2009 at 01:52 PM

    Hi Chirald,

    Please adjust your value category customizing according to the following

    settings

    :

    1) In transaction CJVC, all yellow and/or red lights have to eliminated

    by assigning each cost element/commitment item/statistical key figure

    according to the following rules:

    1.1) Each cost element/commitment item/statistical key figure should

    be assigned to a value category, EVEN if its values should NOT

    be updated to table Project Information Database, table RPSCO.

    In this case please create an assignment to a value category

    and activate its 'suppress' indicator. All values basing on an

    assignment to this value category won't be updated to RPSCO.

    1.2) Each cost element/commitment item/stat. key figure has to be

    assigned exactly once to a value category. Assigning them to

    more or less than one value category will lead to unpredictable

    results.

    1.3) Only

    1.3.1) cost elements of the same cost element type,

    1.3.2) commitment items of the same item category and

    1.3.3) statistical key figures of the same unit of measure

    and the same KF category are allowed to be assigned to

    one value category. Mixed assignments will lead to

    unpredictable results, like mixing costs and revenues in

    columns or rows.

    2) If all yellow and/or red lights in transaction CJVC are eliminated,

    please rebuild the Project Information Database (table RPSCO) by

    transaction CJEN. Without this, changes from 1.1)-1.3) won't have

    any effect.

    3) Please rebuild the assigned values by transaction CJBN.

    Could you also review notes51971, 327081, 676123?

    Thanks a lot and kind regards,

    Enrique

    Add comment
    10|10000 characters needed characters exceeded