on 10-30-2009 11:05 AM
Hi all,
What is the purpose of indicators Alt selection and production version in BOM application (TCode OPJM)?
How system selects a BOM for a production order when both indicators are selected? Can anybody explain with an example.
Thank you.
Anil
Dear Anil,
Alt selection
1) Say for example you have three Alt BOM's for one Header material
2) Now how Choose those, again u need to define Alternative Determination For Multiple BOM's
3) So based on this slection of Alt BOM take's place in MRP
Production version
this settings is for selecting PV's
Regards
kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kumar,
Thanks for your response.
I still have one doubt...
If I create a process order with a specific order type, which has a BOM application say PI01 with both indicators (Atl selection and PV) set, then how the BOM is selected (through validity in Alt selection or through PV)?
Thank you.
Anil