BOMMAT IDOC is not created

389 Views

Hello,

I am trying to create the BOMMAT IDOC out of the BOM changes.

The problem is that if I do that for a specific material BOM it works, but for another it does not create any IDOC.

I do not have any filters in BD64.

The difference between the 2 materials is that the one that does not work is also maintained for SD, WM, and production.

Is the BOMMAT influenced by the fact that the material is maintained also for sales, or others?

The material that works is maintained only for purchasing and MRP.

Thank you for the answers.