on 10-30-2009 6:27 AM
Hi
Pls guide me where do we assign the holiday calender to Personnel subarea
Regards
Seema
Hi,
Please find the IMG path below.
IMG>Time Management>Work Schedule>Work Schedule Rule and Work Schedules>Define Groupings for Public Holiday Calendar.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The Enterprise Structue which you are design like Personal Area and Personal Subarea
based on that you will define the Holiday Calendar for example
you PA is INDIA
under PSA is Maharastra and Punjab and the holiday will differ for both the places at that time you have to define two holiday calendars and assign it to them
the most important part is how you are going to bifuricate the Enterprise Structure
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You need to do this in Table:V_001P_M.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes there is a PATH
in case if u want to know the path through if u know the tabel
SM30 V_001P_H
go to last tab customising click it you will get the sb window again click it without project specification
you will find the nodes there related
if u want to go thru SPRO
check the node under time management